Skip to content

Callie Link

Callie Link keeps several Callie Grams machines in step, so a backup is ready to take over if the main machine fails. One machine is the Main and every other machine is a Backup. Everything the Main fires also fires on its Backups, and each Backup keeps a copy of every project on the Main, media included.

Using Callie Link is perfect for running a disaster recovery setup and also for duplicated audio playback over a larger site.


  1. On the main machine, open Preferences → Callie Link.
  2. Under This machine, choose Link Main.
  3. Check the Link key. One is generated for you, or you can type your own. Use Copy key to copy it for your Backups.
  4. Leave Link port on 9300 unless that port is already in use.
  5. Click Save Link Settings.

Backups connect to this machine’s address on the link port. Allow both UDP and TCP on that port through any firewall.

  1. On the backup machine, open Preferences → Callie Link.
  2. Choose Backup (connect to a Main).
  3. Enter the Main’s address, such as 192.168.1.20 or host.local.
  4. Paste or type the Link key. Capitals, spaces and dashes don’t matter.
  5. Set Link port to the Main’s link port.
  6. Click Save and Connect.

Generating a new key on the Main disconnects every Backup until you give them the new key.


These actions on the Main are sent straight to every Backup:

  • Button presses, with each button’s normal behaviour, including action buttons and Custom Events
  • Stop All, Stop Output, Stop Gang and Stop Group
  • Events and timecode cues
  • Skipping a playlist track
  • Project switches and page changes

Buttons are matched by their position in the grid, so every machine needs the same layout loaded. The status indicator warns you if a layout differs.

Timecode cues only fire on the Main, because each machine’s clock can differ. Backups play the Main’s mirrored action instead. If the Main goes offline, a Backup carries on with its own cues.

By default, what a Backup fires stays on that Backup. To change this, enable Backups’ actions fire on every machine on the Main. Anything fired on a Backup then also fires on the Main and on every other Backup.


Each Backup keeps a copy of every project on the Main as a Link project. These appear on the Link tab of the Projects window, separate from the machine’s own projects on the Local tab.

Link projects use the Main’s numbers with a PRL prefix, so PRJ:003 on the Main is PRL:003 on a Backup. You can switch to one over OSC with /callie/prl/003. See Web API and OSC.

Keep Link projects in step with the Main automatically is on by default. Media downloads straight away, and the loaded project is only replaced when nothing is playing. After the first sync, only the files a Backup doesn’t already have are transferred.

With this option off, changes only arrive when you click Sync now.

Projects removed from the Main are also removed from its Backups.

While the Main is online, a Backup can only open the Link project the Main has open, so nobody plays from a different show by mistake. If the Main switches project while a Backup is playing, the Backup follows when its playback stops.

Local projects can always be opened. If the Main goes offline, a Backup can open any project, so it can carry on alone.

Link projects are read-only on Backups by default. To allow edits, enable Backups can edit Link projects on the Main. An edit made on a Backup is then sent to the Main and on to every other Backup. If the project has already changed on the Main, the Backup’s edit is turned down.

To move a Local project from a Backup to the Main, use Send to Main on the project in the Projects window. The Main’s operator is asked to Accept or Decline, and the request lapses after two minutes.

An accepted project is added to the Main as a new local project. It isn’t loaded, so the running show isn’t interrupted.


A status dot in the header shows the health of the link. Hover over it for a summary, or click it for details. The full status is also in Preferences → Callie Link and on the Link tab of the Projects window.

DotMeaning
GreenThe link is healthy.
SyncingProjects are being copied to this Backup.
GreyThis Main has no Backups connected yet.
AmberNeeds attention, such as a different layout, a Backup offline, or a Backup waiting to follow the Main.
RedAction needed: the Main is offline, project sync failed, or another machine is also acting as Main.

A Backup shows the Main as offline after about three seconds, and keeps running on its own:

  • Everything it has already synced stays available.
  • It fires its own timecode cues.
  • It can open any project.

Connections are protected by the link key, so two shows on the same network can’t trigger each other.

  • Let the first sync finish before the show, as it copies all the media.
  • Check every machine has the same layout loaded.
  • Rehearse a failover: disconnect the Main and check the Backup does what you expect.